Archive forSeptember, 2007

Spreading Mulch – September 18th

We are getting even closer to completion with the playground! Today the workers installed the last few pieces of the structure and assembled a short wall made of black rubber around the base. Then the mulch was moved from the big pile (see previous post) and spread underneath the playground equipment, filling the area inside the black wall.

Now the department in charge of safety for Virginia Beach City Public Schools will inspect the structure.   Once approved for safety, the playground will be ready for use. Until then, yellow CAUTION tape will surround the equipment.

mulch1.JPG  mulch0.JPG 

mulch2.JPG  mulch4.JPG

Comments

The Cement Truck Arrives – September 7th

Today a huge truck arrived. It contained the cement that will be used to fill the support pole holes. Under the hot September sun, the workers used wheelbarrows to move cement from the truck to each hole. 

cement2.JPG   cement1.JPG

cement3.JPG   cement4.JPG

The cement will take about three days to harden.  Then the mulch will be spread underneath the new equipment. We know everyone is anxious to play on the new equipment. It should be ready soon–one day next week.

Comments

Waiting for Cement – September 6th

The new playground is assembled. Yellow CAUTION tape surrounds it because it is not ready yet. Deep holes were dug for the different poles that supsport the equipment and hold everything together. Within the next few days the cement truck will arrive and pour cement into each hole. This will help reinforce our new playground and make it strong and safe.  The cement needs 72 hours to harden before the playground can be used.

redpole.JPG

Yesterday a huge truck delivered wood mulch for the playground area. The mulch will be spread underneath and around the entire playground area.

 mulch.JPG

Comments

It’s Looking Like a Playground (September 5th –noon)

Our playground is looking like a real playground. The workers have made great progress since yesterday.  This picture was taken around lunchtime today. Our students having been watching the progress and can’t wait to have fun on the new playground.

sept-5.JPG

Comments

First Day of School – Construction Begins! (September 4th)

Yippee!  It’s the first day of the new school year and construction of the new playground began today. Lots of workers and lots of hours will help to complete this project by Monday, September 10th

Watch this blog for daily updates this week!

first-day1.JPG

first-day-2.JPG

first-day-3.JPG

Comments